Rajiv Awas Yojana (RAY)


Municipal Corporation Shimla has prepared a Pilot DPR amounting to Rs. 3399.65 lacs for Krishna Nagar Slum under Rajiv Awas Yojna (RAY). Ministry of Housing & Urban Poverty Alleviation (MoHUPA), GOI has approved pilot project (DPR) in the year 2013 for Krishna Nagar Slum. The first installment Rs. 1067.24 lac has already been released in 2012-13 by the State Government to MC Shimla. 


The component wise status is as under:


Sr.

Project Component

Status

1

Construction of proposed Children park for Slum Dweller under RAY in Krishna Nagar:

Work completed

2

Construction of approach road 3.50m width from New Slaughter House to location No 5 in krishna Nagar Shimla including cross drainage work.

Work completed

3

Construction of proposed Community Centre at Krishna Nagar under Rajiv Awas Yojana  ( RAY ) at Shimla ( SH:- C/O Civil Work, site development and WS & SI etc )

Work completed

4

Construction of proposed 88 Dwelling Units on Location No 3 Krishna Nagar under Rajiv Awas Yojana at Shimla ( SH:- C/O Civil work WS & SI Solar System Rain water Harvesting  Tank fire fighting storm water Drainage and site Development complete )

At Location No. 3 in Krishna Nagar,  ward 88 dwelling units were proposed to be constructed. Work was awarded to Sh. N.K Vij, Contractor on dated 08.11.2016. Presently work of 48 dwelling units is complete. The Construction of 40 No.s dwelling units has been proposed to be constructed through RTDC.

5

Construction of Proposed 208 Dwelling units on location No 5 krishna Nagar under Rajiv Awas Yojna at Shimla ( SH:- C/O Civil work WS & SI Solar system ,Rain water Harvesting Tank ,fire fighting ,Strom water Drainage and site development complete )

The work 208 dwelling units were proposed to be constructed and work was awarded to M/S Vishwa Bhumi Engineers on 17.11.2016 at location no. 5in Krishna Nagar ward. Due to heavy Landslide at the proposed site only 16 Dwelling Units can be constructed. RCC Framed structure work of two blocks consisting Dwelling Units in each blocks is in progress. Balance 192 Dwelling Units cannot be constructed as there occurs heavy landslide at this proposed site. Keeping in view the above facts, it need be the remaining dwelling units will be consisting at new site i.e Malyana as per requirement and availability of funds.


 